Update: Summer Building Projects

If you have traveled by the York Suburban High School campus this summer, you may have noticed many building projects in action. Total roof replacement began on May 26.  Work is progressing nicely and on schedule to be completed by August 18.

The athletic stadium turf replacement project was completed on schedule. The old turf reached its life expectancy for safe usage. A secure gate will be installed in August.

 

Other indoor projects include:  new hot water heaters, a new stage curtain, flooring, and rigging in the auditorium, and the installation of new interior doors with secure access control at the high school. Actual construction started May 26. The demolition of doors and frames are on or ahead of schedule. Doors and hardware should arrive the first week of August and new doors for existing frames are expected by mid-August.